Projects

UPDATED QUARTERLY CURRENT PROJECTS REVIEW REPORT

NAME OF PROJECT LOCATION COST OF PROJECT COMPLETION STATUS NOTES
Test on highway road Russia ((N. Novgorod) Free Completed in 2007 Monitoring/Comparison report is being delivered in June 2008
Test on gravel road Georgia and
Krasnodar Oblast (Russia)
$ 50,000 Completed in 2007 Negotiation for further local and rural road 1800 km construction
Leviev Ecoroads Dynamic cone penetrometer Russia,
Moscow

Designing and manufacturing sample unit $12,500 Device is manufactured and tested in 2007-2008 Estimated yearly needs are estimated as 50-60 units per year
Highway from Astana to Yekaterinburg Russia-Kazakhstan $11,100,000 US (Total length with main temporary roads is 200 km Initial main and gravel road design revision Estimated time for construction and monitoring equipment delivery is June 2008. Engineering services all along construction duration (re-designing, rate application and monitoring ).
Rural 6 km. road near Alma Ate Kazakhstan $225 000 Road cross-section design revision Estimated time for construction is July 2008
Soil Brick manufacturing
Plant
Russia,
Costroma
Revision of the
business plan for plant refurbishing
August 2008

Estimated plant capacity is 30,000,000 brick per year
Soil Brick manufacturing
Plant
India Project funding from Israel is negotiated 2008 Estimated plant capacity is 50,000,000 brick per year
Construction of road in small towns Argentina Technology and equipment testing in Patagonia Third quarter of 2008 Total contractual length of roads is around 30 km.
Afghanistan Government Road Project Afghanistan and Tajikistani $20,000,000 US.
Construction team training and construction
2008-2010

Total contractual length of roads is around 500 km. All scopes of engineering services included
Rural road construction and implementation of local premises for soil brick manufacturing Tanzania,
Congo,
Namibia
$250,000 for initial testing, roads construction and brick machines implementation Forth quarter of 2008 Total contractual length of roads is around 1000, including 20 km. during 2008.
All scopes of engineering services included
Technology of concrete blocks hardening for trench pipe construction Tanzania $125,000
2008-2009

Main usage is trench less collectors construction and pipe jacking
Slope of highway construction on unstable soils Russia,
Caucasus
Estimated as $3,000,000 US Design to be provided for re-designing in 3 quarter of 2008 Special technologies for compaction on slopes and its monitoring are in questions
Testing on the airstrip at Moscow Airport Russia,
Moscow Oblast
$50,000 Initial offer is under consideration 3 quarter of 2008
General offer to Moscow city Road Construction Council Russia,
Moscow
Under estimation   2008 -2011
Service road for S-Petersburg Power Plant Russia,
Leningrad Oblast
Initial engineering offer from the Client and general Distributor’s Agreement are under negotiations Should begins in 2008 All scopes of engineering services requested
Road construction Kirgizia, Beshkeck
& Latvia
(Riga and its suburbs)
$37000 US per one km. of road
Two layers asphalt motorway is designed
3 quarter of 2008 Soil-cement layer is to be replaced by soil layer, stabilized by enzymes admixes. All scopes of services included
In-situ soil compaction and road profile monitoring technologies USA, Germany,
Russia, Kazakhstan
$200,000 US 2008-2009  
Road construction Malaysia, Indonsia,
& Mongolia
$37000 US per one km. of road 3 quarter of 2008 Soil-cement or soil-gravel layers are to be replaced by soil layer, stabilized by enzymes admixes. All scopes of services included
Manufacturing of concrete internal retaining units (for underground tunnels and collectors). Bangladesh,
Dacha
Joint R&D with local and US companies   Under negotiation
Road constriction Central Africa countries $37,000 per km/ Under final estimation for 340 km of rural roads construction 2008-2012  
Marketing for moisture content in-sity measurement USA $ 16,000 June 2008